Commercial Tenant Improvement Painting Case Study – Fremont Crossing, Seattle
Project Overview
Element PCC completed a commercial tenant improvement painting project at Fremont Crossing in Seattle’s Fremont neighborhood. Performed for Foushee Construction, the scope involved interior office painting for a Level 2 buildout executed under an active construction schedule.
Project address: 310 Florentia Street 2nd Floor
Seattle, WA 98109
Quick Project Facts
Project Type: Commercial tenant improvement painting
General Contractor: Foushee Construction
Location: Fremont neighborhood, Seattle, Washington
Contract Value: Approximately $30,000
Project Duration: April 21, 2025 – May 29, 2025
Scope of Work
Interior commercial office painting including new drywall and existing wall finishes, limited accent wall coatings, and coordination with general contractor sequencing.
Labor and Performance
Labor efficiency significantly exceeded expectations, with approximately 200 hours used against a 450-hour budget. Proper sequencing and minimal trade interference contributed to performance.
Materials and Coating Systems
Primary wall finishes utilized Sherwin-Williams ProMar 200 Eggshell, with accent areas finished using Sherwin-Williams Duration Satin to ensure coverage and durability.
Results
The project was completed on schedule with strong profitability, approved change orders, and minimal punch list items.
Conclusion
The Fremont Crossing project serves as a benchmark example of Element PCC’s ability to deliver efficient, high-quality tenant improvement painting services in the Seattle commercial market.